Friday, June 12, 2015

Well Update

After nearly seven months of drilling and over a year of work, the test hole for the well on #12 is complete and at a depth of 1340'.  The well was tested last week for potential output and water quality, with results indicating the potential to produce 100-200 gal/min from water sources above 800’.  Below 800’ the test results indicate only limited amounts of brackish water.    Such tests do not actually test the water; surrounding rock formations are tested and from that data potential output and water quality is calculated. Actual output and water quality cannot be quantified until we develop and utilize the well.  

Possible Production
  • 100 gal/minute pumping 24hrs/day will produce 144k gallons
  • 200gal/minute pumping 24hrs/day will produce 288k gallons
  • We use an average of 300k gallons of water per day on the golf course, May-September

The information we have encourages us to complete the well to a depth of 800’, filling the hole below with concrete in order to prevent the brackish water from contaminating the usable water above 800’.  As stated throughout this entire process the well is not an absolute and may go dry or not recharge itself at any given time.   

We will not be able to utilize the well water or any other alternative source without a storage tank and a pump station. In order for us to develop such onsite infrastructure the Shareholders will need to approve the necessary funds. A detailed presentation of our options and a Shareholder vote are planned to take place within the next 90 days.

We appreciate your understanding during this process and look forward to completing the entire water project as soon as possible.  

Tuesday, March 17, 2015

Well Update

The well project has been slow going the past two weeks.  After changing the drill rig from a traditional drill to an air hammer, Maggiora Brothers were able to break through the granite and drill several hundred additional feet.  After breaking through the granite the well drillers decided to not case the well below the granite, thinking the material below the granite would be hard.  The material below the granite turned out to be very soft and the well collapsed.  The drill bit and several cones broke off and are stuck in the bottom of the well.  The well drillers tried to retrieve their equipment for over a week, with no success, as the well continued to collapse every time they went down.  Over the past several days they were able to case the rest of the well and are now attempting to retrieve the cones and drill bit.

We are currently at 800' and the well is producing 20-40 gal/minute.  This is far from the 200 gal/minute we are hoping for.  The data shows the majority of water to be at the 1200'-1300' depth.  We want to reiterate this is a test drill and there is the possibility we will not find any water.  As frustrating as this is it's completely out of our control.  Maggiora Brothers wants to complete this well as soon as possible so they can move on to their next job.  We will send out an update as soon as we find out any additional information.  Thank you for your patience and understanding.

Wednesday, January 21, 2015

The Well Exploration is Under Way

After almost 7 months of waiting the drilling started early this morning on the test well.  For the next 7-14 days the drill will make its way down 1500' through sand and rock.  Once the test well is complete we will send a device down to take measurements.  The data from this device will be analyzed and a well will be designed to accommodate the estimated production if any.  Even with the best technology available there is a possibility we will not hit water or enough to justify developing a well.
Please be aware of signage around the area.  It may be different from your last round.  Currently there is a white line painted across the front of the work area.  Everything above the white line in mandatory ground under repair.  Please do not get close to the equipment or engage workers.  The area is an active work site and can pose a danger.  If you have any questions about the well or the process please contact Justin Mandon or Scott Hoyt.


Wednesday, November 26, 2014

The Well Driller is Here

If I had a dollar for every time Ken Woods asked me about the well driller I could retire and buy a share at Pasatiempo.  It's been a long and frustrating wait but the well driller is on property preparing the site for the drill rig.  The actual drill will be here next week depending on the weather and access to the site.  This is the beginning of a process we expect to last 4-6 weeks.  Cart traffic around the area could be diverted at anytime so please pay attention to signs or instructions from Ken and his staff.  We are in the process of building a temporary tee on the right side of #12 at 245 yards.  This should make for a fun drivable par 4.  Keep in mind the well drillers will be working everyday until the well is completed.  We apologize in advance for any inconvenience this may cause while playing the 11th green and 12th tee.

Temporary Tee #12

First Day