Tuesday, July 18, 2017

Water Project Update

The water project has been moving at a blistering pace since the end of the winter rains.  We are on track to finish construction mid August and begin our 2 week startup procedure.  There are numerous requirements from the city, county and state before we turn on the treatment facility but the list is getting smaller each and every week.



Completed

  • 500k gallon tank
  • All building foundations and walls
  • Pump station 
  • Filters
  • Underground piping and electrical
In Progress
  • Finish work on all buildings
  • Above ground piping 
  • Sewer connection 
  • Finish grade 
  • Landscaping
  • PG&E connection 
  • Cart path
  • #14 gold tee
We are extremely excited about our current state of the water project.  If you have any questions or would like to see the project up close please contact myself or Scott Hoyt.